Upcoming Footpath and Roading Upgrades in Hikurangi
- Sharlene

- Jan 28
- 2 min read
Hikurangi is set for a busy few weeks of long‑awaited improvements, with both King Street footpath replacements and a full reseal of George Street scheduled for early 2026. These works will bring safer, smoother access through the village, but they will also create temporary changes for drivers, pedestrians, and local businesses.
This combined update outlines everything you need to know.
King Street Footpath Replacement
Start date: Monday, 19 January 2026
Duration: Approximately 4–6 weeks
Location: Southern side of Four Square to the southern side of Hikurangi Takeaways
What’s Happening
Contractors will remove and replace the footpaths along this section of King Street, including new kerbing and driveway entrances. Work will be completed in segments, beginning at Hikurangi Takeaways and progressing toward Four Square.

Access and Parking
Pedestrian access to all businesses will remain open throughout the project.
Parking on the shop side of King Street will be restricted to allow machinery to operate safely.
Visitors and locals are encouraged to use the vacant yard beside the hall and the hotel carpark during this period.
Traffic control will support safe pedestrian movement.
Two‑way traffic will remain open, with only minimal disruption expected.
These upgrades have been a long time coming, and we encourage the community to welcome and support the Red Dell team as they complete this important work.
George Street Reseal Works
Roadworks name: George Street Hikurangi Reseal
Contractor: Fulton Hogan (on behalf of Whangārei District Council)
For further questions: Please contact WDC or Fulton Hogan directly.
When It’s Happening
Sunday 8 February – Night works
Monday 9 February & Tuesday 10 February – Day works
Little George & Hill Street: Tuesday 10 February, 7am–8pm
Residents will receive a letter drop before works begin, and VMS boards will be in place five days prior to notify drivers.
What to Expect
Fulton Hogan will be resealing the full length and width of George Street. To avoid damage to vehicles, residents are strongly encouraged not to park on the George Street carriageway during the reseal period.
Sunday 8 February, 4pm – approx. 2am (Night Closure)
George Street will be closed at the SH1 turnoff into Hikurangi.
Access into the village from SH1 will be via King Street (northern end).
Resident access will be maintained, with traffic controllers onsite.
Monday 9 & Tuesday 10 February, 7am–8pm (Day Works)
George Street will be open under manual traffic control (stop/go).
A temporary speed limit will apply due to the loose chip and temporary surface.
Little George and Hill Street will also have sealing works on Tuesday, with resident access maintained.
Stay Updated
For progress updates, photos, and notices, keep an eye on our community Facebook page and the council website:
Fulton Hogan Northland 09 470 0700